Landfill design and construction parameters | Distance between wells | 5 m |
Distance between groups of wells | 15 m |
Distance from the first and the last wells of a pad to the landfill border | 80 m |
Landfill width | 75 m |
Landfill height | 2 m |
Landfill construction speed | 600 m3/d |
Drilling rig mobilization time | 30 d |
Landfill specific cost | 167 USD/m3 |
Fixed cost of pad construction | 1.7×106 USD |
Drilling and completion parameters | *Well drilling time | 30 d |
*Well completion time | 20 d |
*Well drilling cost | 0.83×106 USD |
*Well completion cost | 0.5×106 USD |
Drilling rig short shift duration | 1 d |
Drilling rig long shift duration | 2 d |
Drilling rig demobilization time | 10 d |
Drilling rig short shift cost | 28333 USD |
Drilling rig long shift cost | 43333 USD |
Drilling rig demobilization cost | 166667 USD |
Technological parameters of wells | *Initial oil flow rate | 20, 50, 90 t/d |
*Oil production decline rate | 25%, 40%, 45%, 50%, 60%, 70% |
*Initial water cut | 1% |
*Liquid production increment | 0.3% |
* Water cut at well shut-in | 90% |
*Oil density | 850 kg/m3 |
*Water density | 1010 kg/m3 |
Economic parameters | Price of oil | 200 USD/t |
Specific operational expenditures (liquid based) | 16.7 USD/m3 |
Discount rate | 10%, 15%, 20% |
Time step | 1 d |
Modeling period | 20 a |