Optimization of well pad design and drilling - well clustering
ABRAMOV Aleksandr
Table 1 Technical and economic parameters of the model.
Classifi-
cation
Technical and economic parameter Value
Landfill design and
construction parameters
Distance between wells 5 m
Distance between groups of wells 15 m
Distance from the first and the last wells of a pad to the landfill border 80 m
Landfill width 75 m
Landfill height 2 m
Landfill construction speed 600 m3/d
Drilling rig mobilization time 30 d
Landfill specific cost 167 USD/m3
Fixed cost of pad construction 1.7×106 USD
Drilling and
completion parameters
*Well drilling time 30 d
*Well completion time 20 d
*Well drilling cost 0.83×106 USD
*Well completion cost 0.5×106 USD
Drilling rig short shift duration 1 d
Drilling rig long shift duration 2 d
Drilling rig demobilization time 10 d
Drilling rig short shift cost 28333 USD
Drilling rig long shift cost 43333 USD
Drilling rig demobilization cost 166667 USD
Technological
parameters of wells
*Initial oil flow rate 20, 50, 90 t/d
*Oil production decline rate 25%, 40%, 45%, 50%, 60%, 70%
*Initial water cut 1%
*Liquid production increment 0.3%
* Water cut at well shut-in 90%
*Oil density 850 kg/m3
*Water density 1010 kg/m3
Economic
parameters
Price of oil 200 USD/t
Specific operational expenditures
(liquid based)
16.7 USD/m3
Discount rate 10%, 15%, 20%
Time step 1 d
Modeling period 20 a