Predictability of well construction time with multivariate probabilistic approach
|
LUU Quang-Hung,LAU Man Fai,NG Sebastian P.H.,TING Clement P.W.,WEE Reuben,THEN Patrick H.H.
|
|
|
Table 2 Statistics of phases of interest available in 192 selected operations in the dataset.
|
|
Phase | Number of record | Duration/days | Minimum | Maximum | Mean | Median | Variance | Skewness | Kurtosis | CH | 49 | 0.02 | 0.86 | 0.35 | 0.31 | 0.04 | 0.54 | -0.27 | SH | 132 | 0.02 | 13.83 | 1.87 | 1.28 | 4.23 | 2.88 | 11.00 | IH | 130 | 0.01 | 21.17 | 5.18 | 4.29 | 16.94 | 1.41 | 2.14 | PH | 132 | 0.01 | 15.31 | 3.68 | 3.43 | 6.59 | 1.19 | 2.71 | CC | 112 | 0.01 | 3.06 | 0.78 | 0.77 | 0.27 | 1.11 | 2.62 | SC | 132 | 0.05 | 4.65 | 1.55 | 1.39 | 0.70 | 0.90 | 1.18 | IC | 104 | 0.02 | 11.08 | 2.38 | 2.16 | 2.46 | 2.09 | 8.44 | PC | 23 | 0.08 | 5.42 | 1.81 | 1.65 | 1.78 | 0.99 | 0.77 |
|
|
|